‘Big bang’ to make Sheffield’s Sevenstone reality

Grand designs: Original artist's impression of part of the Sevenstone new retail quarter scheme for Sheffield which has been on hold since 2009.

Grand designs: Original artist's impression of part of the Sevenstone new retail quarter scheme for Sheffield which has been on hold since 2009.

SHEFFIELD’S new Sevenstone retail quarter will be built in double-time to help make up for delays which have dogged the flagship scheme.

Sheffield Council chief executive John Mothersole told The Star the project will be constructed as a ‘big bang’ - all at once rather than in phases as originally envisaged.

The change will mean the entire scheme is finished in two years instead of up to four.

Sevenstone, first announced in 2006, has been on hold since 2009 due to the global economic crisis.

But a decision by the Government to allow up to £30 million of future income from business rates to be provided in advance to off-set risk means the council insists Sevenstone is now viable.

Mr Mothersole, who held crunch talks with Hammerson earlier in the month, said: “The aim is to have no phasing and to build the entire scheme at once - a kind of big bang.

“Work would begin next year and be finished by 2016.”

Mr Mothersole added that the council and Hammerson are involved in ‘sensitive high level negotiations which we aim to come to a conclusion very quickly’ so the project can begin.

The Star understands a decision on when work will begin is to be made in the next few weeks.

John Lewis is likely to move to a new store as part of the scheme and its current site redeveloped.

Concern had been expressed by opposition councillors about the length of delay to Sevenstone because Hammerson had announced other schemes in Leeds and Croydon while the Sheffield scheme has been on hold.

Sevenstone in numbers:

Proposed completion date Hammerson and Sheffield Council are working towards - 2016

Estimated cost of the original proposals - value of final scheme not yet revealed - £600

Years of delay to the project, first phases of which were planned to be finished in 2011 - 5

What do you think about the Sevenstone project?

Email: letters@thestar.co.uk


 
loading...
Find It

"Business owner? - Claim your business and Advertise with us"

In association with qype logo

Looking for...

Featured advertisers

Jobs

Search for a job

Motors

Search for a car

Property

Search for a house

Weather for Sheffield

Thursday 23 May 2013

5 day forecast

Today

Light showers

Light showers

Temperature: 4 C to 9 C

Wind Speed: 21 mph

Wind direction: North

Tomorrow

Light showers

Light showers

Temperature: 4 C to 9 C

Wind Speed: 25 mph

Wind direction: North east

Press Complaints Commission

This website and its associated newspaper adheres to the Press Complaints Commission’s Code of Practice. If you have a complaint about editorial content which relates to inaccuracy or intrusion, then contact the Editor by clicking here.

If you remain dissatisfied with the response provided then you can contact the PCC by clicking here.

Sheffield Telegraph provides news, events and sport features from the Sheffield area. For the best up to date information relating to Sheffield and the surrounding areas visit us at Sheffield Telegraph regularly or bookmark this page.